|
Period 16 1.8. – 14.8.2001
|
the operator’s explanations (a
clogged bag filter) are accepted. report to the Public Prosecutor
|
|
Period 17 14.8. – 29.8.2001
|
-
does not
conform
-
Following
this incidence of exceeding the permitted value, the operator was
questioned
and
voluntarily stopped the furnace on 13 September 2001. The contractor
responsible
for
the building work was summoned.
-
For the
record, the breach during period 16 occurred because of a clogged bag
filter.
The
unclogging carried out should have resolved the problem. A detailed
investigation
into the causes of the breach revealed a defect in the bag filter’s
internal by-pass joints,
an
unforeseeable accident. These joints were therefore replaced and a general
inspection
of
the bag filters was carried out to ensure that they were in good
condition.
- Once
the reasons for the breach had been identified and steps taken to remedy
the
defects,
authorisation was granted on 19 September 2001 to start up the furnace
again.
The ISSeP
(Institut
scientifique de service public – Public Utility Scientific Institute)
will take a spot check sample to confirm that the measures taken have been
effective.
The
test will be performed on cartridge 19, because cartridge 18 was sampled
before
the
breach and the defect were discovered, and therefore before the problem
was resolved.
|
Period 18
29.8. – 12.9.2001 |
|
|
Period 19 12.9.- 26.9.2001
|
-
does not
conform
-
A reading
of 0.71 was obtained for furnace No. 2, which had already experienced
an operational problem during periods 16 and 17. It was taken out of
service. It
appears that the problems with the operation of the bag filter, which
caused the
previous breaches, had still not been resolved. However, but steps are
currently
being taken to remedy this. Furnace No. 2 will not be started up again
until the
repairs are completed.
|
Period 20 26.9. – 10.10.2001
|
|
|
Period 21 |
|
Period 22 24.10. – 6.11.2001 |
|
|
Period 23 -
26 |
|